Comparison ledger
YES 1000P, YES R3, side by side. Every value shown is drawn from the cited encyclopedia entries.
| Attribute | 1000PYES | R3YES |
|---|---|---|
| OEM | YES | YES |
| Category | Wet Processing / Clean | Wet Processing / Clean |
| Wafer size | — | — |
| Process node | — | — |
| Introduced | — | — |
| Production run | — | — |
| Lifecycle | — | — |
| Lifecycle milestones | 1998 Acquisition | — |
| Control system | — | — |
| Generation | — | — |
| Family | YES 1000P | YES R3 |
| Specifications | ||
| Model | 1000P[1] | — |
| System type | Plasma cleaning system[1] | Plasma cleaner / plasma cleaning system[3] |
| Shelf configuration | Four 16 x 16 inch shelves[1] | — |
| Total capacity | 1024 square inches[1] | — |
| Control system | PLC driven with plain English real time process readout and diagnostics in the event of system abort[1] | Sequential microprocessor[3] |
| Number of shelves | 4[1] | — |
| Shelf size | 16 x 16 inches[1] | — |
| Power | 1000 W[2] | — |
| Configuration | Parallel plate[2] | — |
| Operation modes | Active, RIE, Downstream[1] | — |
| Sample size range | From smallest semiconductor chip to large flat panels[1] | — |
| Control | — | Sequential microprocessor[3] |
| Program storage | — | Up to 90 separate one- or two-gas programs in memory[3] |
| Power supply | — | 500 Watt[3] |
| Plasma gas inputs | — | Two standard; optional third input[3] |
| Backfill input | — | Standard[3] |
| Electrode sets | — | Two 12-inch square electrode sets standard[3] |
| Sample tray capacity | — | Two 12 x 12 in. sample trays; total capacity 325 sq.in.[3] |
| Sample trays | — | Two 12 x 12 in.; total capacity 325 sq.in.[3] |
| Controller | — | Sequential microprocessor; up to 90 stored one- or two-gas programs[3] |
| Process gas and modes (UC Santa Barbara configuration) | — | Oxygen; downstream and direct plasma cleaning[4] |
| Position in series | — | Smallest of the series; pilot run quantities[3] |
| Equipment type | — | Plasma cleaning system[5] |
| Stored programs | — | Up to 90 separate one- or two-gas programs[3] |